Construction of an assembly chamber for tunneling to the future Golyanovo metro station has begun

Translation. Region: Russian Federal

Source: Moscow Government – Government of Moscow –

An important disclaimer is at the bottom of this article.

The construction of an assembly chamber has begun for the launch of two tunnel boring machines (TBM) that will carry out the excavation of transfer tunnels on the extension section of the Arbatsko-Pokrovskaya metro line from the Shchyolkovskaya station to the future Golyanovo station. This was reported by the Deputy Mayor of Moscow for Urban Development Policy and Construction Vladimir Efimov.

"To drive the tunnels between the Shchelkovskaya and Golyanovo stations, shields with a diameter of six meters will be used. The work will begin with the starting pit at the Shchelkovskaya station, located on Uralskaya Street, and will end in the dismantling and shield pit at the Golyanovo station. The length of both tunnels with turnaround dead ends will be 2.6 kilometers. The start of the first tunnel boring complex is scheduled for November of this year," said Vladimir Efimov.

After the excavation, the excavation of the pit for the construction of a traction and step-down substation and a structure for connecting to the existing Shchelkovskaya station of the Arbatsko-Pokrovskaya metro line will continue.

“Currently, the installation of enclosing structures for the installation chamber pit is underway at the launch site using the ‘wall in the ground’ method,” added Maxim Gaman, General Director of Mosinzhproekt JSC.

According to the project, the Golyanovo station is shallow-level and will be built using open-pit methods in the area of the intersection of Ussuriyskaya and Sakhalinskaya streets.

The Golyanovo station includes an island platform and two underground vestibules. Each vestibule will have elevators for comfortable movement of passengers with limited mobility, as well as parents with baby carriages. Behind the station, turnaround dead ends will be built for the rolling stock of the Arbatsko-Pokrovskaya metro line.

Golyanovo will improve transport accessibility for 230 thousand Muscovites and will help relieve the Shchyolkovskoye Highway and Shchyolkovskaya station by about a quarter.

Earlier, Sergei Sobyanin announced the start of construction of the station "Golyanovo" Arbatsko-Pokrovskaya metro line.